(d) If action is required, annotate the action needed in the "action-
needed" column.
(e) When the action has been taken, enter the date and your initials in
the "action-taken" column.
(4)
Blocks 10A through 10C, leakage current to paddles. Refer to
figure 2-7.
(a) Measure and record the leakage current to the paddles in the
equipment's ON and OFF positions.
(b) Circle the unacceptable values.
(c)
If no action is required, place an "X" or "√" in the "ok" column.
(d) If action is required, annotate the action needed in the "action-
needed" column.
(e) When the action has been taken, enter the date and your initials in
the "action-taken" column.
(5)
Block 11, output energy (Watt-seconds). Refer to figure 2-8.
Figure 2-8. DA Form 5624-R, block 11.
MD0358